Construction Progress:
The contractor has completed clearing along the new sanitary sewer route. Work during the next few weeks will include:
* Installation of the silt fencing to prevent erosion near Home Depot Drive
* Dewatering at bore and jack pits located in East Paris and along Woodland Creek Dr
* Installation of earth retention systems at bore and jack pits near Woodland Creek buildings 4013 – 4019
* Construction of the 54″ sanitary sewer from Woodland Creek building 3318 heading east toward Patterson
* To date, the project is on schedule.